September 2016

S M T W T F S
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1
View All

Stormwater Project Updates:

  1. Walnut/Myrtle/Evergreen Stormwater Improvement Project Update - 9/29/16

    Scheduled Rock Blasting was performed at the Elmhurst Quarry on Friday, September 16th at 4:25 p.m. Ludwig Explosives, a contractor who has been hired by the City of Elmhurst, performed the scheduled rock blasting in conjunction with the...

  2. Geneva Avenue Stormwater Improvement Project Update - 09/29/16

    Construction activities have begun.  Silt Fence installation, tree removal at the detention pond area, installation of the storm sewer outfall on Geneva, and utility potholing have all been completed to date.  The contractor is scheduled to begin the...

  3. Crescent/Cambridge Stormwater Improvement Project Update - 9/29/16

    Last week construction activities began.  Installation of construction fence, survey layout, tree trimming/removal, and delivery of construction equipment all have been completed.  The tree removal was necessary to accommodate the detention basin...

  4. York/1-290 Stormwater Improvement Project Update- 9/29/16

    Excavation and utility work continues.  To date the majority of the excavation and storm sewer installation has been completed.  Next week the contractor will begin the installation of the new stormwater pumping station manhole.  City staff continues...

View All