Stormwater and Sanitary Project Updates:

  1. Southwest Elmhurst Stormwater Mitigation Project - Phase II - 03-22-19

    The contractor completed final testing of the pumps and float sensors for the storm water pump station.  Training for City staff is being scheduled in the next few weeks and once completed; the city will take over operations of the pumping station. ...

  2. Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 03-22-19

    The contractor has continued the installation of the 60-inch storm sewer from the detention basin towards Butterfield Road.  At the same time, the boring contractor has successfully completed the boring of the 60-inch storm sewer under Butterfield...

  3. Southwest Elmhurst Stormwater Mitigation Project - Phase II Update 02-22-19

    Work this week included final electrical connections and installation of the pumps. The pumps are set to be turned on late next week for their first trial run and for testing. After the pumps are operating per the design then City staff will be...

  4. Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 02-22-19

    Work commenced again this week after the contractor took a couple month break due to the winter weather conditions. This week the contractor excavated for the new pre-cast concrete wet well at the southeast corner of the basin of Euclid Avenue.  The...