Earthwerks completed the excavation and installation of the underground chambers this week.  With this milestone reached, over 725 pieces of concrete pieces were delivered and installed in less than 30 days.  Next week, the contractor will continue with stone delivery and backfill around and above the concrete chambers.  The contractor anticipates stone backfill will be completed next week.