College View Stormwater Improvement – 08.06.21 Project Update:

Earthwerks has completed the installation of the forcemain from the pump station to the existing storm sewer.  With this work complete all of the major work outside the fenced in area is done, minus small restoration items.  The installation of the underground detention chambers has also begun.  It is anticipated that the underground detention system will be completely installed by the mid-September.

08.06.21

8-6-21 friday highlights