Saylor/Swain/Vallette – Project Update - 09.21.20

Posted on September 21, 2020 at 7:50 AM by Barbara Petrucci

A major milestone was achieved this week when the contractor completed the installation of the StormTrap chambers.  The final connection of the 54-inch storm sewer into the StormTrap system will occur next week with the delivery of a special order 54-inch connector pipe. Also next week, the final storm sewer improvements in the parkway and the street along Swain Avenue should be completed.  Once the entire storm sewer infrastructure is installed, the contractor will start to focus on restoration of the area around the StormTrap system.

SSV 9-21-20 UPDATE