Aug 21

Saylor/Swain/Vallette – 08.21.20 Project Update

Posted on August 21, 2020 at 1:16 PM by Barbara Petrucci

This week, the contractor completed the installation of the new water services lines, from the City’s watermain to the b-box, where lead lines existed and the homeowners coordinated replacement of their portion of the service.  The contractor also started to frame up the sidewalk, curbs and aprons in preparation for the concrete to be poured and finished on Monday.

Finally, the contractor started working on the 4 lots in preparation for the excavation and installation of the underground StormTrap system next week.  It is anticipated they will take delivery and install 25 sections of the concrete chambers a day and the entire system installed in 2 weeks.

SSV 8-21-20 UPDATE