Saylor/Swain/Vallette Project Update 07.24.20

Posted on July 24, 2020 at 2:39 PM by Barbara Petrucci

The demolition of the 4 houses on Swain has been finalized with all the foundations and driveways removed, along with leveling off of the site. Also completed this week was the installation of the large box culverts on Crescent Ave.

The storm sewer work on Saylor has begun and should continue into early next week.  Nicor has also started to install new gas services to houses in front of the newly relocated gasmain; this work will also continue into next week.

Next week, the contractor will start to prepare Crescent Ave in anticipation of pouring concrete curbs and sidewalk to start the restoration process on this street.