Jul 16

Saylor/Swain/Vallette Project Update 07.16.20

Posted on July 16, 2020 at 9:48 AM by Barbara Petrucci

Currently the contractor has begun installing the box culverts under Crescent Avenue this week.  These twin 10’ x 8’ box culverts will be ran from Swain Avenue to Saylor Avenue along Crescent and will provide complimentary detention volume to the larger detention site to be located at 633-645 S. Swain Avenue.
SSV - Crescent 7-16-20Additionally, the house demo of the four City-owned properties along Swain Avenue started on Thursday this week.  The demolition of the houses, which will only take a couple days to complete, follows the removal of asbestos from the structures in accordance with IL EPA regulations.

SSV - Demo Photos 7-16-20