Harrison Street Stormwater Improvement Update 3.24.17

Posted on March 24, 2017 at 4:59 PM by Barbara Petrucci

Harrison Street Stormwater Improvement Update

The majority of the earth excavation and haul-off is complete, so residents can expect to see much less trucking on Harrison Street as the project continues.

The contractor will now work on backfilling behind the wall, making drainage connections, installing the concrete cap on top of the wall, then restoring the site.