Harrison Street Stormwater Improvement Project

Installation of the sheet piling for the stormwater basin is now complete.  The Contractor is now hauling dirt off the site in order to create additional storage volume in the basin.  This work will involve approximately 60 trucks per day, driving west on Harrison Street to access the site, getting loaded with dirt, then continuing west on Harrison Street and out to Butterfield Road. Please be aware of the trucks and take every precaution to keep clear.

After the dirt haul-off is finished, a concrete cap will be placed on the wall and then restoration of the site will begin. The attached notice and renderings went out to residents of Harrison Street and Lexington Street to provide information on the fence and landscaping that will be installed around the basin.

Harrison Street Stormwater Construction Notice

Harrison Street Stormwater Fence Renderings