Harrison Street Stormwater Improvement Project Update 12/12/16

Posted on December 12, 2016 at 4:58 PM by Barbara Petrucci

Roadway work at the intersection of Yorkfield/Chatham and along Harrison Street was completed recently, including; installation of storm sewer, curb and gutter, and asphalt pavement.  Final restoration of parkways will occur when the weather permits.

The contractor has begun preparing for the installation of the new sheet pile walls by excavating and flattening out the bottom of the detention basin.  Installation of the walls could begin as early as December 15th, weather permitting.