York/I-290 Stormwater Improvement Project Update 11.14.16

Posted on November 14, 2016 at 8:08 AM by Barbara Petrucci

The transformer pad for the lift station was installed by ComEd.  Electrical and mechanical components for the lift station are still being fabricated, but there a temporary pump in place in case a storm was to fill the basin.  The basin is now functional and will fill up with water in a large rain event, thus reducing flooding on York Road.  Grass is starting to grow nicely throughout the basin.