The contractor removed curb, sidewalk, and necessary pavement on Chatham Ave and Harrison Street.  Tree removal and trimming also took place.  The contractor began pouring new curb and sidewalk at the intersection of Chatham and Yorkfield today, and work will continue in the coming days. 

Curb on Harrison Street will likely be poured beginning next week.  We will notify residents when they will need to move cars out of their driveway for curb and driveway apron installation.  Be on the look-out for notices next week.

 