Crescent/Cambridge Stormwater Improvement Project - Update 11/2/16

Posted on November 2, 2016 at 2:48 PM by Barbara Petrucci

Crescent/Cambridge Stormwater Improvement Project

Excavation of the new detention basin in York Commons Park continues.  The contractor has also bored two 36” steel pipes under the CN railroad tracks.  When the project is completed, these 36” pipes will carry floodwater that previously collected on Crescent over to the new detention basin.  After some delay in relocating their gas main on Crescent Ave, Nicor is now finishing up their work.  Once Nicor is done, the sewer contractor will be able to continue with installing the 48” storm sewer on Crescent Ave.