Madison Early Childhood Education Center Stormwater Improvement Project

The contractor finished tunneling the 48” storm sewer under Madison Street.  He then continued storm sewer installation on Washington Street, south of Madison towards the new detention basin.  Work on Washington Street is now taking place north of Madison Avenue.  Between Madison and McKinley there will be a lot of work in the coming weeks.  A new sanitary sewer will be installed, then water services will be replaced, then two new storm sewers will be installed.  Excavation of the detention basin is scheduled to begin Friday, November 4th and last about two weeks.  Truck traffic will be heavy on Adams Street during the basin excavation.  Residents are encouraged to avoid Adams Street if possible, and be aware of trucks coming and going to the project site.

Madison Early Childhood Update Photo 11 2 16