Geneva Avenue Stormwater Improvement Project Update - 09/29/16

Posted on September 29, 2016 at 11:51 AM by Barbara Petrucci

Construction activities have begun.  Silt Fence installation, tree removal at the detention pond area, installation of the storm sewer outfall on Geneva, and utility potholing have all been completed to date.  The contractor is scheduled to begin the storm sewer installation on Third Street, between Clinton Avenue and Geneva Avenue, within the next several business days.  Pond excavation will commence following the storm sewer installation on Third Street and is tentatively expected to begin the week of October 10th.