Excavation and utility work continues.  To date the majority of the excavation and storm sewer installation has been completed.  Next week the contractor will begin the installation of the new stormwater pumping station manhole.  City staff continues to coordinate with ComEd on a new electrical feed for the pumping station and also with Meade electric on some conduit relocations for the IDOT lights.