York/I-290 Detention Project Update - 8/23/16

Posted on August 23, 2016 at 11:44 AM by Kassondra Schref

The bids for this project were opened on August 2, and were approved by the City Council on August 15th.  This project is adding 18.5 acre-feet of detention at a cost of $1,351,495.  Start of construction is anticipated for early September 2016 and substantial completion by the end of this year.