The open house for this project was held on August 18th, and bids were opened on August 16th.  The PWBC will be considering this bid at their August 22 meeting, with City Council consideration on September 6th.  Construction is anticipated to begin in late September or early October.  This project will add 5 acre-feet of detention providing relief to 11 homes.