Walnut/Myrtle/Evergreen: Construction Update

Posted on May 20, 2016 at 3:38 PM by Madonna Nero

Walnut/Myrtle/Evergreen Stormwater Improvement Project:

walnut myrtle evergreen 052016

Now that all of the underground piping has been installed on the residential streets, restoration work is underway. Landscaping and sod were installed on Myrtle Avenue. Curb installation, sidewalk, and concrete driveway aprons were installed on Second Street and Evergreen Avenue. Second Street and Evergreen Avenue should be paved with asphalt binder by the end of next week, weather permitting.

Work also progressed near the quarry connection this week with installation of a 10’ diameter manhole and 72” diameter concrete pipe.