Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04.19.19

Posted on April 19, 2019 at 2:54 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04-19-19

Due to poor soil conditions near the church parking lot, the contractor has concentrated on installing the 60-inch storm sewer parallel to Butterfield Road.  To help with the soil conditions in the area near the parking lot, dewatering wells have been installed.  It is anticipated dewatering operations will take 10-14 days to eliminate enough ground water to allow the remaining storm sewer pipe to be installed.