Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04.05.19

Posted on April 5, 2019 at 2:00 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04-05-19

The underground boring contractor completed the second (smaller) casing under Butterfield and the forcemain was installed within the casing pipe.  This completes the major underground improvements on the north side of Butterfield.  Pipe installation of the 60-inch storm sewer from the detention basin to the storm sewer previously bored under Butterfield at Bryan Street continues; it is anticipated that all of the 60-inch pipe installation will be finished by the end of April.
   