Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 03-22-19

Posted on March 22, 2019 at 3:43 PM by Barbara Petrucci

The contractor has continued the installation of the 60-inch storm sewer from the detention basin towards Butterfield Road.  At the same time, the boring contractor has successfully completed the boring of the 60-inch storm sewer under Butterfield Road.  The boring contractor has removed his equipment from the boring pit to allow a large 8-foot diameter storm sewer structure to be installed.   Once the 60-inch storm sewer work in this area is completed, the boring contractor will be back to bore a 24-inch casing for the forcemain installation under Butterfield Road.