Southwest Elmhurst Stormwater Mitigation Project - Phase II Update 02-22-19

Posted on February 25, 2019 at 11:39 AM by Barbara Petrucci

Work this week included final electrical connections and installation of the pumps.  The pumps are set to be turned on late next week for their first trial run and for testing.  After the pumps are operating per the design then City staff will be trained on the operations of the pumps.