Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 02-22-19

Posted on February 25, 2019 at 11:26 AM by Barbara Petrucci

Work commenced again this week after the contractor took a couple month break due to the winter weather conditions. This week the contractor excavated for the new pre-cast concrete wet well at the southeast corner of the basin of Euclid Avenue.  The contractor excavated the ground and installed a 37 ft. deep steel shoring system for safe excavation.  On Friday the contractor used a large crane to lift and place pieces of the pre-cast concrete wet well structure inside the shoring; thereby completing the installation of the structure. 