Southwest Elmhurst Stormwater Mitigation Project - Phase I - Update 11.09.18

Posted on November 9, 2018 at 2:27 PM by Barbara Petrucci

With all sewer work north of Harrison complete, the contractor completed paving the roadway and associated restoration along Bryan, Jackson, Prospect, and Parkside. At the basin site, the contractor has been excavating for two weeks and will continue at least through the end of November. The next few weeks will also include the delivery and installation of the block retaining walls that will be placed within the basin. In December, once the basin is nearing completion, the contractor will begin connecting the newly installed storm sewer pipes along Bryan Street to the basin in order to make the basin functional.