Southwest Elmhurst Stormwater Mitigation Project-Phase II - Update 10.09.18

Posted on October 9, 2018 at 10:10 AM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project-Phase II - Update 10.09.18

The rough excavation, stone rip-rap installation, topsoil installation, storm sewer installation, and force main installation was completed last week. The new stormwater pumps that will drain the basin are currently being fabricated and concrete restoration is anticipated for this week. Until the pumps are installed the basin will temporarily have ground water in the bottom. The Jackson Street pavement will be resurfaced at the same time as the Phase I project directly to the east to create a seamless pavement surface. Finally, the new 6’ black vinyl-coated permanent fence will be replacing the temporary fence as one of the last items of the project.

SESMP Phase II Update_1_ 10.9.18