Southwest Elmhurst Stormwater Mitigation Project-Phase I - Update 10.09.18

Posted on October 9, 2018 at 8:50 AM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project-Phase I - Update 10.09.18

The underground contractor is currently working on Parkside and Prospect to complete a small amount of sewer work as the sewer work nears completion. The asphalt base course was paved last week along Bryan, and the restoration behind the new curbs will take place over the next week. Once all of the sewer work is complete, the final pavement surface will be installed over Jackson and Bryan at the same time; which is expected to take place over the next couple weeks. The installation of the slurry wall at the basin near Royal York Condominiums was completed last week, and the full scale excavation has begun.