Posted on August 25, 2017 at 8:51 AM by Barbara Petrucci

Installation of the underground concrete vault is complete.  The vault is online and will take water if a flooding event occurs. 

At present, the lift station is incomplete.  The contractor is ordering the correct pumps and control panel.  If a flood event was to occur and the vault was to fill with storm water, City staff would pump the vault down after the rain event.

Washington Street Website Update Photo 07 23 17