Pine Street / Avon Road Stormwater Improvement Project Update 7.3.17

Posted on July 3, 2017 at 11:25 AM by Barbara Petrucci

Excavation of the detention basin is now 50% complete.  The contractor will be installing underdrain in the bottom of the basin next week along with continuing excavation.  On First Street, the underground contractor plans to begin installing sewer between Geneva and Berteau after the 4th of July holiday.  Storm sewer installation down First Street, to the west, will continue into the middle-to-end of July and will include detours and temporary closing of the Poplar RR crossing.