Currently, mass excavation efforts are underway to create the Stormwater detention basin.  This activity will continue for the next week or two.  Additionally, storm sewer installation continues this week between the new basin location and Geneva Avenue along the Union Pacific railroad tracks.  Once this storm sewer installation is complete, the contractor will then start working westward with the storm sewer installation down First Street towards Pine Street and Avon Road.  Storm sewer installation on First Street is anticipated to take several weeks and will involve road closures along First Street and at the railroad crossing at Poplar Avenue.