Last week construction activities began.  Installation of construction fence, survey layout, tree trimming/removal, and delivery of construction equipment all have been completed.  The tree removal was necessary to accommodate the detention basin installation.

This week the contractor has been stripping the topsoil at the detention basin location, delivering concrete storm sewer pipe, and has begun excavation for the jacking pit on the south side of the railroad tracks.

Next week the contractor will make the storm sewer connection in York Street and begin placing storm sewer piping along the south side of the detention basin (just north of the York Commons parking lot).  If weather permits the contractor will also begin the excavation of the detention basin.

Crescent_Cambridge 1 Crescent_Cambridge 2

Aug 23

York Commons Project Update - 8/23/16

Posted on August 23, 2016 at 11:44 AM by Kassondra Schref

The informational open house was held on April 20, 2016.  See the attached exhibits. The bids for this project were opened on August 4, and were approved by the City Council on August 15th.  This project is adding 11 acre-feet of detention at a cost of $2,108,151.  Start of construction is anticipated for early September 2016 and substantial completion by the end of this year.

York Commons Concept Improvement Plan

York Commons Proposed Conditions Drainage

York Commons_Existing_Proposed Inundation Area

Apr 21

Exhibits From 04/20/2016 Open House Now Available for Viewing

Posted on April 21, 2016 at 1:44 PM by Madonna Nero

The exhibits from the Open House on the York Commons Stormwater Improvement Project from 04/20/2016 are now available for viewing.

York Commons Park Stormwater Improvement Exhibits

Tag(s): York Commons