Apr 29

Webster Ave Update: Detention Basin

Posted on April 29, 2016 at 12:01 PM by Madonna Nero

Webster Ave Basin 04-29-2016
Grass is beginning to grow at the detention basin. The silt fence surrounding the three inlets at the bottom of the basin will be removed when turf is established.

Tag(s): Webster, Update, Basin

Mar 17

Webster Ave Update: Landscape Restoration

Posted on March 17, 2016 at 2:33 PM by Amanda Stuber

Landscape restoration is anticipated to be completed in the upcoming weeks (weather permitting).
Feb 09

Webster Ave Update: Detention Basin in Action!

Posted on February 9, 2016 at 3:44 PM by Amanda Stuber

The Webster Avenue Detention Basin took on significant water for the first time during  last week's rain event on Tuesday, February 2nd.  The facility handled the rain as planned.  Final restoration of the basin will take place in the spring/early summer.


Webster Basin in Action