Installation of the concrete wall cap is nearly complete in the west half of the basin, and installation of the cap is underway in the east half. Once the cap install is complete the final grading and landscaping will be completed.

Harrison update 6-30-17

Jun 09

Harrison Street Stormwater Improvement Project Update 06.09.17

Posted on June 9, 2017 at 1:25 PM by Barbara Petrucci

This week fence installation began around the perimeter of the basin and will continue into next week.

Harrison Street Stormwater Update 6 9 12

Sections of the concrete cap for the wall are also being set by the contractor.  Once this work is completed, final grading and landscaping will take place.

 
Harrison Street Stormwater Update 6 9 12-b


Mar 24

Harrison Street Stormwater Improvement Update 3.24.17

Posted on March 24, 2017 at 4:59 PM by Barbara Petrucci

Harrison Street Stormwater Improvement Update

The majority of the earth excavation and haul-off is complete, so residents can expect to see much less trucking on Harrison Street as the project continues.

The contractor will now work on backfilling behind the wall, making drainage connections, installing the concrete cap on top of the wall, then restoring the site.