Oct 09

Southwest Elmhurst Stormwater Mitigation Project-Phase II - Update 10.09.18

Posted on October 9, 2018 at 10:10 AM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project-Phase II - Update 10.09.18

The rough excavation, stone rip-rap installation, topsoil installation, storm sewer installation, and force main installation was completed last week. The new stormwater pumps that will drain the basin are currently being fabricated and concrete restoration is anticipated for this week. Until the pumps are installed the basin will temporarily have ground water in the bottom. The Jackson Street pavement will be resurfaced at the same time as the Phase I project directly to the east to create a seamless pavement surface. Finally, the new 6’ black vinyl-coated permanent fence will be replacing the temporary fence as one of the last items of the project.

SESMP Phase II Update_1_ 10.9.18

Sep 26

Southwest Elmhurst Stormwater Mitigation Project-Phase II Update 9.26.18

Posted on September 26, 2018 at 9:32 AM by Barbara Petrucci

The detention basin excavation is now complete and a majority of the stone along the bottom has been installed to prevent erosion. The contractor has begun installing the sewers from the street to the basin and will also be installing the force main which will drain the basin after rain events. The final limit of the stone bottom was modified based on field conditions and a new rendering of the basin is shown below. With the new brick paver parking lot at Christ United Methodist Church now complete and striped the parking lot is now available for use by the church.  Work is expected to heavily impact Jackson Street traffic for approximately 2-3 more weeks while the underground work is completed and the road is restored. After that point, the remaining work will include restoration of the grass areas and fence installation. The contractor is continuing to coordinate with Jackson Elementary School during drop-off and pick-up times to ensure the children’s safety.

SESMP Phase II Update 9.26.18SESMP Phase II Update_2_ 9.26.18
Aug 28

SESMP Phase II Update August 27, 2018

Posted on August 28, 2018 at 2:26 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project-Phase II

Full-scale detention basin excavation began this week and is anticipated to take about 2 weeks. So far the contractor has excavated about 40% of the new basin.  With the new brick paver parking lot at Christ United Methodist Church now complete, the construction traffic is now contained to Jackson Street.  With the increased truck traffic, the contractor is coordinating with Jackson Elementary School during drop-off and pick-up times to ensure the children’s safety.
SESMP Phase II Update 8.27.18
Southwest Elmhurst Stormwater Mitigation Project - Phase II 
Southwest Elmhurst Stormwater Mitigation Project - Phase II