Sep 13

Southwest Elmhurst Stormwater Mitigation Project - Phase I - 09.12.19

Posted on September 13, 2019 at 8:38 AM by Barbara Petrucci

The detention pond improvements are nearing completion.  The perimeter fencing is close to being finalized with only the various gates needing to be installed.  The landscaping around the perimeter of the site has been installed and the low profile prairie grass within the basin has started to become established.  The pump station is moving closer to completion; the pumps have been installed and the contractor is working with ComEd to make the final electrical connection.

9-12-19 Phase I Update
Apr 19

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04.19.19

Posted on April 19, 2019 at 2:54 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04-19-19

Due to poor soil conditions near the church parking lot, the contractor has concentrated on installing the 60-inch storm sewer parallel to Butterfield Road.  To help with the soil conditions in the area near the parking lot, dewatering wells have been installed.  It is anticipated dewatering operations will take 10-14 days to eliminate enough ground water to allow the remaining storm sewer pipe to be installed.

SESMP Phase 1 - 4.19.19



  

 

 

 


Apr 05

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04.05.19

Posted on April 5, 2019 at 2:00 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04-05-19

The underground boring contractor completed the second (smaller) casing under Butterfield and the forcemain was installed within the casing pipe.  This completes the major underground improvements on the north side of Butterfield.  Pipe installation of the 60-inch storm sewer from the detention basin to the storm sewer previously bored under Butterfield at Bryan Street continues; it is anticipated that all of the 60-inch pipe installation will be finished by the end of April.
   

SESMP Phase I - 4-5-19