Aug 25

Washington Street Stormwater Improvement Project Update 08.25.17

Posted on August 25, 2017 at 8:51 AM by Barbara Petrucci

Installation of the underground concrete vault is complete.  The vault is online and will take water if a flooding event occurs. 

At present, the lift station is incomplete.  The contractor is ordering the correct pumps and control panel.  If a flood event was to occur and the vault was to fill with storm water, City staff would pump the vault down after the rain event.

Washington Street Website Update Photo 07 23 17

Jun 21

Washington Street Stormwater Improvement Project Update 06.19.17

Posted on June 21, 2017 at 9:23 AM by Madonna Nero

Asphalt paving on Washington Street, north of Madison, began today. The first lift of asphalt should be installed by later this afternoon. In the next week or two, parkway landscape restoration and the second lift of asphalt installation should be completed.

Washington Street Website Update Photo 6-19-17





Jun 13

Washington Street Stormwater Improvement Project Update - Video 06.13.17

Posted on June 13, 2017 at 9:50 AM by Barbara Petrucci

Please view the attached Earthwerks drone video which shows the progress of the Washington Street Stromwater Improvement Project from the beginning of the project.
 
https://www.youtube.com/watch?v=QxNjOPXlhqM